All lines in the file including code, text, comments, and blank lines

Language Breakdown

Language Total Lines Code Lines Comment Lines Blank Lines Percentage
assembly 513 352 268 55 100.0%
Total 513 352 268 55 100.0%

Code Composition Analysis

Total Lines Over Time - Changes Per Interval

Total Lines Over Time - Growth

Commit Activity Over Time

📊 Project Cost Estimation Models

Based on 352 lines of code (0.4 K)

COCOMO (1981)

Effort: 0.9 person-months
Schedule: 2.4 months
Team Size: 0.4 people
Cost Estimate: $11,180
Mode: Semi-detached
Barry Boehm's foundational model using empirical coefficients based on project type.

COCOMO II (2000)

Effort: 1.0 person-months
Schedule: 3.6 months
Team Size: 0.3 people
Cost Estimate: $11,664
Exponent (B): 1.060
Updated model with scale factors for modern development practices and reuse.

Function Point Analysis

Function Points: 6 FP
Effort: 0.3 person-months
Schedule: 1.5 months
Team Size: 0.2 people
Cost Estimate: $3,300
Primary Language: assembly
Measures functionality independent of technology using standardized function points (~60 LOC/FP for assembly).

SLIM Model

Effort: 0.9 person-months
Schedule: 0.1 months
Team Size: 6.7 people
Cost Estimate: $11,180
Productivity Index: 5,000
Uses Rayleigh curves and Putnam's software equation emphasizing optimal staffing over time.

Putnam Model

Effort: 5.2 person-months
Schedule: 1.4 months
Min Schedule: 1.2 months
Team Size: 3.6 people
Cost Estimate: $62,110
Technology Factor: 8,000
Lawrence Putnam's lifecycle model based on productivity and minimum development time constraints.

Model Comparison Summary

Model Effort (PM) Schedule (Months) Team Size Cost (@ $75/hr)
COCOMO 0.9 2.4 0.4 $11,180
COCOMO II 1.0 3.6 0.3 $11,664
Function Points 0.3 1.5 0.2 $3,300
SLIM 0.9 0.1 6.7 $11,180
Putnam 5.2 1.4 3.6 $62,110
AVERAGE 1.7 1.8 0.9 $19,887

Note: These are theoretical estimates based on historical models. Actual project costs vary significantly based on team experience, requirements clarity, technology choices, and project management practices. Use these as rough guidelines for planning and budgeting, not as precise predictions.

Recent Commits

Commit User Date Total Lines
20655 bo 2021-03-22 13:32 513
20654 bo 2021-03-22 13:31 513
20653 bo 2021-03-22 13:30 513
19279 bo 2020-03-30 02:37 513
19277 bo 2020-03-29 21:04 509
Back to Projects